Yunker Farm Park
Status: Current & Ongoing
Location: Yunker Farm Park
Estimated Completion: Ongoing
Project Overview:
Status: Current & Ongoing
Location: Yunker Farm Park
Estimated Completion: Ongoing
Project Overview:
Status: Current
Location: Lemke Park
Status: Current
Location: Cornerstone Bank Arena
Estimated Completion: September 1, 2026
Project Overview: Complete replacement of the existing mechanical systems for the ice arena which includes new compressors, cooling towers, and the addition of a dehumidification system for the arena.
Status: Complete December 2024
Location: Anderson Softball Complex
Project Overview: Updated lights are being installed in the two south fields at Anderson Softball Complex. Underground work began in mid-July and is anticipated to be complete in early August. Lights will be installed in mid to late October.
Status: Completed December 2025
Location: Tharaldson Little League Playground
Project Overview: Removing and replacing the playground equipment with new, modern structures to provide a safer and more engaging play environment. The playground is closed until construction is complete.
Status: Completed June 2026
Location: Longfellow Park
Project Overview: Remove and replace the deteriorating asphalt parking lot on the west side of the park with new asphalt surfacing, improving overall condition, usability, and durability.
Status: Completed May 2026
Status: Future | Starting Late-August 2026
Location: Pointe West Park
Expected Completion: September 2026
Project Overview: Remove the existing outdated playground and replace it with a new, durable, high-quality playground designed to enhance play value and user experience.