Projected timeline for the Fargo Parks Sports Center: 

  • December 7 - Bid opening 
    • If bids come in favorable the following timeline continues.
  • January 11 - Award bids for construction (Park Board Meeting)
  • Spring 2022 - Projected groundbreaking 
    • 20-22 month build out
  • Early Summer 2024 - Phase I Grand Opening
  • January 2025 - Phase II Grand Opening

*Timeline projections as of December 7, 2021